|
For
the Sake of Beauty
Some Turn Lanes Will
Be Lost in $22.3 Million Project
“It has been done but the report has not been published yet.”

Convention Center drive is just one of the
thoroughfares the city has plans for. Photo by Angie Hargot
By Angie Hargot
South Beach
residents can expect to see more roads being torn up over the next
few years near Lincoln Road and the Convention Center. The purpose?
A better-looking City Center, project planners say.
The Miami Beach
Capital Improvement Projects (CIP) Office unveiled the next step in
the City Center project that has been steadily trudging forward for
more than two years and is slated to wrap up construction in
December 2009, during a Community Design Review Workshop held Nov.
29.
Project architect
Jim Hill led a presentation of the city’s plans for the City Center
redevelopment district, located south of Dade Boulevard. The designs
under review mostly centered on widening and resurfacing sidewalks,
adding some “bump-outs,” and converting some existing turn lanes
into irrigated and landscaped medians “the width of a full lane of
traffic,” Hill said. It’s all toward the endgame of making the
streets more “pedestrian-friendly,” he said.
Coupled with water
and sewer main replacement and storm water drainage renovations, the
City Center improvements are projected to cost the city about $22.3
million, and, in construction phases, will tie up various streets in
the area for the next three years.
During
construction, half of each street will be temporarily closed,
traditionally for the length of a few city blocks at once, as the
streets are repaved or other construction occurs, said CIP Director
Jorge Chartrand. After construction, traffic “will not be affected,”
he said.
The expected effect
on traffic has been determined through designers’ “experience,”
“following city and county code,” and a study, according to
Chartrand.
The project’s
actual construction pattern most likely won’t be determined until a
contractor wins a bid for construction that planners “can work
with.” The completion date for the bid and award phase of the
project is currently December 2007.
However, the
contents of the traffic study remain a mystery. “It has been done,”
Chartrand told the SunPost. “But the report has not been
published yet. When the report is published it is given to the
engineers, who can adjust the plans accordingly. The engineers have
been in contact with Public Works.”
An official in the
Public Works Department explained the department is currently
conducting traffic counts for the City Center area — basically
counting vehicle traffic in a given area to then apply formulas for
predicting future traffic needs — in order to make recommendations
to the CIP. The department is also responsible for analyzing the
effects that changes such as those to medians and sidewalks create.
According to the department, it’s difficult to improve the capacity
of streets due to lack of space to add lanes. But improving
conditions for pedestrians can help traffic patterns in one
kind-of-obvious way – it keeps people out of the way of cars.
With the report not
yet completed, the designs have, so far, hit one little snag — the
length of one street’s “storage lane,” a sort of staging area for a
turn lane. One official in the Public Works Department expects to
see the report ready in about two months.
Chartrand likened
the probable traffic problems relating to construction to those that
affected Washington Avenue during its renovation last year. “Of
course there was disruption,” he said.
The streetscaping
improvements also include that all sidewalks will be replaced with
“Miami Beach Red Concrete,” flush red brick-paved crosswalks and
“Lincoln Road satellite” streetlights. Landscaping changes will
include both shade trees and various species of palms. And while
“most streets are too narrow to landscape the swales,” Hill said,
whenever possible swales will also see some renovations.
The city may get a
sidewalk along the area of 19th Street from Convention
Center Drive to Meridian, “one of the things we tried to accomplish
was to try to get a continuous sidewalk, at least on one side of the
street,” Hill said.
No street space is
being lost on Convention Center Drive, where the most drastic impact
is expected, due to lanes being “wider than the city code
[requires],” Chartrand said. “They have to be a minimum of 10 feet
wide; they’re about 16 or 18 or 12 feet wide,” he said.
Chartrand said the
whole City Center project is the result of citizens’ desire to
beautify the area, as expressed during community meetings.
The plans were
generally well received by the few Miami Beach residents present at
last week’s CIP meeting.
“I
think it’s a great plan,” Ray Breslin, president of the Collins Park
Neighborhood Association, told the SunPost. “This all started
with money from the General Obligation Bond back in 1998, and we’re
just starting to see some of [the improvements]. It’s like, ‘Where
are they?’ But Rome wasn’t built in a day,” he said.
Comments? E-mail
angie@miamisunpost.com.
|